PUBLIC NOTICES
Contractors from South Jersey Gas will be working in Elsinboro Township installing gas lines for the availability of Natural Gas to Township Residents.
Below is a schedule of where the crews should be working through the middle of April and contact information if there are any issues or questions for the work crews:
ULS will have 2 crews working our Salem expansion phase 1 project Monday 4/6/26 and will be adding an additional crew Tuesday 4/7/26 to Thursday 4/9/26 (3 total crews). ULS will also be working extended days Friday 4/10 to Sunday 4/12 with one crew possibly 2.
The crew hours will be 7 AM to 530 PM Monday to Sunday..
Natural Gas NOTICE
Location of Crews:
Crew 1 will be working on Fort Elfsborg-Salem rd. from Riverview Dr to fort point road
Crew 2 will be working on Fort Elfsborg- Hancocks Bridge Rd. from Fort Elfsborg-Salem rd and will be heading East. To about 2400’ West of Amwellbury Rd.
Crew 3 will be working on Sinnickson Landing Road from Tilbury to Fort Elfsborg-Salem Rd.
All traffic patterns will be stop and go with flagging operation and access for residence and businesses.
Any questions please done hesitate to ask.
Our field supervision contact information
John Day- 443-553-5227
George Barats- 215-688-2327
Phone: 856-935-2200 Fax: 856-935-9011
619 Salem Ft-Elfsborg Rd
Salem, NJ 08079


Remember to check on elderly or disabled neighbors in your community during extreme cold or heat and during an emergency.
Reach out for township info and assistance





